From: Billy Wasson <br />To: Mryan; Pmilne; rfranke <br />Date: Thu, Jul 20, 2000 11:06 AM <br />Subject: Weekly update <br />,~~ ~.,~ ~~' <br />l.,l <br />~,,;y,,` . ~~~'`'.~i'~;~..~..~ _. '`- <br />The second floor should be totally complete by the end of this week and next week the contractor wants to <br />do a"punch IisY' on 2nd. floor and the hearing/a.v. rooms. <br />Casework will begin on the 3rd. floor next week and the lockers in the transit area will begin next week as <br />well. Carpet installation on the 4th. floor will begin next week. Paver installation on the Mark Hatfield Plaza <br />will be complete this week and next week will begin in the transit mall and the Court street sidewalk areas. <br />Testing and balancing of the hvac systems will begin next week. <br />All for now. Thanks. <br />Billy <br />CC: Bwasson; I:HammJ@Cherriots.org; I:pughc@cherriot... <br />