~ addition to direct costs, up to the following amounts may be added to the Contractor's or sub-contractor's <br />direct costs to cover Overhead as defined above for work performed with their own forces: <br />Labor. . . . . . . . . . . .15 % <br />Equipment......10% <br />Materials........10% <br />When an authorized subcontractor performs work, the Contractor will be allowed a supplemental mazk-up <br />on each piece of subcontract work covered by the change order of 5%. <br />These payments made to the Contractor will be complete compensarion for overhead, profit, and all other <br />costs that were incurred by the Contractor or by other forces furnished by the Contractor, including <br />subcontractors. T'hese payments apply to all change order work. No other reimbursement, compensation, <br />or payment will be made. Deducrive changes are those which reduce the scope of the work. All deductive <br />changes will be negotiated using the percentages for labor, equipment, material and subcontractor mark-ups <br />above. <br />Please let me now as soon as possible if I can proceed with my change order pricing per the above <br />guidelines. <br />incerely, <br />Dave s <br />Project Manager <br />Courthouse Square <br />• Dh/gml <br />r 1 <br />U <br />