Laserfiche WebLink
11l22l99 Courthouse Square County Transit <br /> Approved COR / CO Log o.ssss 0.3064 <br /> A PPROVED COUNTY TRANSIT Contamination <br />COR CO AMOUNT DESCRIPTION OF CHANGE ALLOCATION A LLOCATION Total <br />COR # 1 1 $ 2,530.00 Decomission, removal and disposal of UST encountered on 3-15-99 $ 2,530 $ - $ 2,530 <br />COR # 2 1 $ 1,765.00 Resolve gas line conflicts during sewer line relocation $ 1,224 $ 541 <br />COR # 3 5 $ 14,135.00 Excavate, remove and dispose of three tanks in the NW corner of the site $ 14,135 $ - <br />COR # 4 1 $ 12,215.00 Removal and disposal of contaminated soils-203.9 c.y. $ ~2,2~5 $ ' $ ~2,2~5 <br />COR # 5 1 $ 4,982.00 Decomission, removal and disposal of UST encountered along s. blockface $ 4,982 $ - $ 4,982 <br />COR # 6 1 $ 3,450.00 Increase compressive strength of footing pads from 3,000 to 5,000 psi $ 2,393 $ 1,057 <br />COR # 7 5 $ 6,966.00 Additional dewatering costs due to overexcavation $ 4,832 $ 2,134 <br />COR # 8 5 $ 1,876.00 Owner's share of partnering session $ 938 $ 938 <br />COR # 9 2 $ 16,112.00 Removal and disposal of contaminated soils-268.54 c.y. $ 16,112 $ - $ 16,112 <br />COR # 10 5 $ 1,394.00 Provide cavity wall insulation at exterior masonry walis of rooms 1209, 1219 and 1239 $ 967 $ 427 <br />COR # 11 15 $ 265.00 Provide door, wall and electrical revisions to second floor per PR #2 $ ~~ $ $~ <br />COR # 12 2 $ 685.00 Demolition of water vault along Court street $ 475 $ 210 <br />COR # 13 5 $ (700.00) Delete sump pump at elevator #1 $ (486) $ (214) <br />COR # 14 14 $ 1,362.00 Provide ductwork and supply fan revisions per PR #1 $ 945 $ 417 <br />COR # 15 <br />COR#16 <br />COR # 17 <br />2 <br />$ <br />41,470.00 Removal and disposal of contaminated soils <br />$ <br />41,470 <br />$ <br />- <br />$ 41,470 <br />COR # 18 5 $ (18,723.00) VE proposal #1-Delete low "E" coating on #3 surface of bus mall glass canopy system $ (12,986) $ (5,737) <br />COR # 19 5 $ (1,744.00) VE proposal #1-Replace 1600 amp bus duct with conduit and wire for feed to rooftop equip. $ (1,210) $ (534) <br />COR # 20 3 $ 214,993.00 ' Excavation of unsuitable subgrade/fill in areas of unsuitable or contaminated soils $ 159,414 $ 55,579 $ 33,600 <br />COR # 21 4 $ 27,697.00 Removal and disposal of contaminated soils-461.62 c.y. $ 27,697 $ - $ 27,697 <br />COR # 22 5 $ 5,193.00 Provide couplers at top of parking level columns for future north pad development $ 3,602 $ 1,591 <br />COR # 23 5 $ (440.00) Delete PT tendon locators $ (305) $ (135) <br />COR # 24 8 $ 5,292.00 Slab transition revisions $ 3,671 $ 1,621 <br />COR # 25 <br />COR # 26 <br />5 <br />$ <br />993.00 Revise column ties after fabrication <br />$ <br />689 <br />$ <br />304 <br />COR # 27 5 $ 538.00 Provide column tail revisions $ 373 $ 165 <br />COR # 28 6 $ 32,437.00 Provide six parallel parking stalls wl covered walkway -relocate future job trailers to Church $ 22,498 $ 9,939 <br />COR # 29 5 $ 9,534.00 Revise column reinforcement detail $ 6,613 $ 2,921 <br />COR # 30 5 $ 2,775.00 Provide added rebar at isolation joints $ 1,925 $ 850 <br />COR # 31 11 $ - Provide modifications to public works package per City's requirements $ - $ - <br />COR # 32 11 $ 4,608.00 Provide access hatch and revisions to plumbing and sprinkler system $ 3,196 $ 1,412 <br />COR # 33 5 $ (1,081.00) Delete link seal and ESP-1 $ (750) $ (331) <br />COR # 34 9 $ 1,607.00 Add (4) hot water hose bibs per PR #8 $ 1,115 $ 492 <br />COR # 35 5 $ 6,074.00 Revise columns to go to roof level at grids O/11 and O/12 $ 4,213 $ 1,861 <br />COR # 36 5 $ (2,547.00) Revise column type at grid J-10a $ (1,767) $ (780) <br />COR # 37 9 $ 31,336.00 Provide sump pit per PR #9 $ 21,735 $ 9,601 <br />COR # 38 5 $ 790.00 Provide reinforcing at SOG beneath columns $ 548 $ 242 <br />COR # 39 5 $ 2,053.00 Provide added footing and column $ 1,424 $ 629 <br />COR # 40 <br />