Laserfiche WebLink
Courthouse Square <br />A Marion County/Salem Area Transit <br />Joint Development Project <br />To: Marion County Board of Commissioners <br />From: F. Wasson, Project Manager <br />Date: Apri13, 2000 <br />Re: Request approval of Change Order #21 <br />Recommendation: Approval of change order #21 in the amount of $36,900. <br />Background: <br />Change order #21, copy attached, will add $36,900 to the contract with Pence Kelly. A summary <br />of the most significant items follows: <br />1. Item #1 will be a deduct to the contract for $3,392. We found that the fire rating, per city code, <br />could be reduced on the building lobby. <br />~ 2. Item #2 for $10,327 is a Transit only cost, it modifies their operations room. <br />~.c~ i5 ~ 3. Item #4, per a LEED requirement, will add VOC (volatile organic compounds) sensors to the <br />` air handling systems of the building. <br />4. Item #6 will be a deduct to the contract for $4,997, we changed most hand dryers to paper <br />towel dispensers. <br />,,~N 5 ~ 5. Item #8 adds conduit and mounting platforms for CCTV equipment per their directions and <br />will add $3451 to the contract. I have requested that CCTV reimburse this amount to the project. <br />6. Item #19 adds $6388 to the contract to develop the air quality plan for the project per the <br />LEED requirement. I have requested that Solid Waste reimburse this amount. <br />