Y <br />~ Courthouse Square Manager's Meeting <br />Apri130, 1997 <br />Present: Randy, Elyn, David, Dan, Tracy, Mike and Peggy <br />Abatement & Demolition: <br />Randy started the meeting with discussing the demolition contract status with Staton <br />Construction. The plan was to have them start tomonow on May 18`. David has ca11 in <br />to Ron Richie that has not been returned. Contract has not been signed, and we need to <br />know when is he planning to be on-site. There also needs to be a meeting involving the <br />demolition contractor and the abatement contractor to clarify schedules and time frames. <br />ACTION: David to follow up with Staton Construction to get signed contract and also <br />to work towazds setting up meeting between abatement and demolition contractors. <br />It appears that another contractor/contract has been left out or forgotten. Foss <br />Environmental had a bid for removal of freon from air conditioners, removal of ballasts, <br />paint cans, and other hazardous materials. It appears we do not have a signed contract <br />for this portion of environmental work. It needs to fit into what Rex Allen is doing and <br />the demolition phase. Kathleen originally got an estimate from Foss Environmental. <br />The contract is now bigger than originally estimated by Foss. Previous discussions <br />resulted in facilities management performing a portion of these tasks. Mike and Tracy <br />reported that facilities management is doing the freon removal starting today. Bob had <br />received inventory of all items required to be completed. We need to let Kathleen know <br />that facilities management will do the freon portion and the will be able to re-use the <br />refrigerant later on. Discussion was held as to why hazardous material removal portion <br />was separated from the asbestos removal. David stated it has always been a separate <br />component. We need to get a handle on who will provide this service and/or will it need <br />to go out for bid. This should have been in the original rfp. <br />The freon removal should take the rest of this week and maybe go into ne~rt week. They <br />are following the abatement movement around the building. There may be a delay in <br />starting of the demolition work by a few days. Randy stated we need to fit this work into <br />the process as quickly as possible. <br />ACTION: David to follow up with Kathleen on the particulazs of the contract for <br />hazazdous material removal and then will follow up with Tracy and Elyn. <br />In earlier discussions, Jim Sears was going to be bringing in a consultant, Debby Allen to <br />work with them on the recycling phase. To date there has not been a contract signed. <br />ACTION: David to check and follow up with Jim today on status. <br />There is some concern about using exemptions for contracts that may affect eligibility for <br />