<br />Courthouse Square
<br />Court 8~ High Street
<br />Satem, Oregon
<br />Arbuckle Costic Architects, Inc
<br />Desi n Development Probable Cost Estimate
<br />Architectural Cost Consultants, LLC
<br />James A. Jerde, AIA - Stanley J. Pszczolkowski, AIA
<br />6441 SW Canyon Court, Suite 103
<br />Portland, Oregon 97221
<br />Phone 503) 297-7210 Fax (503) 297-7187
<br />Estimate Date: R18-Aug-98
<br />Document Date: 23-Ju1-98
<br />Print Date: 18-Aug-98
<br />Print Time: 05:44 PM
<br />Construction Start: Spring 99
<br />Ground Levei 23,249
<br />Second Floor 32,088
<br />Third Floor D ~~~ 32,088
<br />Fourth Fioor 32,088
<br />Fifth Floor 32,012
<br />Penthouse 1,818
<br />Total Gross Area 153,343 sf
<br />Buildin Shell 8 Core Quanti Unit CosUUnit Cost Total Comments
<br />
<br />MASONRY
<br />
<br />Concrete Masonry Units
<br />8" cmu backup @ gmd flr windows
<br />674 sf 10.00 6,740
<br />' 6.74~'
<br />Subtotal 6,740 30 So ' a0 SO $6,7a0
<br />Brick
<br />brick veneer 31,503 sf 17.50 551,303 55~,303
<br />@ columns
<br />soldier course 3,962 sf 23.00 91,126
<br />2,252 If 27.00 60,804 9~,t26
<br />s0,8oa
<br />Subtotal 703,233 ' SO ' 30 Sd ' $0 $7U3,233
<br />
<br />TOTAL - MASONRY 5709,973 ' SO SO 30 So 3709,973 4.63
<br />
<br />METALS
<br />
<br />Structurat steel
<br />penthouse roof framing
<br />6.4 ton 3,000.00 19,089
<br />~9,089
<br />assume 7.0 #/ sf
<br />metal deck '
<br />penthouse roof
<br />moment connections
<br />shear studs 1,818 sf 2.00 3,636
<br />ea 750.00 0
<br />ea 5.00 0 3,636
<br />o
<br />o
<br />NIC - verify
<br />NIC - verify
<br />misc. bracing, baseplates, etc. 0.6 ton 3,000.00 1,909 1,909
<br />stair treads
<br />SE & SW typ stair 1st to 5th flr 188 risers 105.00 19,740 79,~ao
<br />SW stair 5th flr to roof 24 risers 95.00 2,280 2,280
<br />stair landings
<br />SE & SW typ stair 1 st to 5th flr
<br />SW stair 5th flr to roof
<br />816 sf 30.00 24,480
<br />204 sf 30.00 6,120
<br />24,a8o
<br />B,t2o
<br />Subtotal 77,254 0 0 tl° ` 0 77,254 0.50
<br />Building Shell & Core Detail Estimate - Page 5