<br />Courthouse Square Architectural Cost Consultants, LLC Estimate Date: R18-Aug-98
<br />Court & High Street James A. Jerde, AIA - Stanley J. Pszczolkowski, AIA Document Date: 23-Ju1-98
<br />Salem, Oregon 6441 SW Canyon Court, Suite 103 Print Date: 18-Aug-98
<br />Arbuckle Castic Architects, Inc Portland, Oregon 97221 Print Time: 05:44 PM
<br />Design Development Probable Cost Estimate Phone (503) 297-7210 Fax (503) 297-7187 Construction Start: Spring 99
<br />
<br />Parking Level One 70,793
<br />Gross Area 70,793 sf
<br />Parkin Quanti Unit CosUUnit Cost Total Comments
<br />
<br />DEMOLITION
<br />remove utilities
<br />sanitary sewer 370 If $6.00 $2,220 2,220
<br />storm 340 If 6.00 2,040 2,a40'
<br />water 300 If 6.00 1,800 1,800'
<br />gas 370 If 6.00 2,220 2,22~'
<br />hazardous material removal sum 0.00 0 0 NIC - By Others (if required)
<br />Subtotal $8,280 ' $0 $~ $8,280'
<br />TOTAL - DEMOLITION 58,280 ' $0 $0 ' $8,2g0 0.12
<br />
<br />SITE WORK
<br />Building related earthwork
<br />temp. shoring @ perimeter sf 0.00 0 0 NIC - assume not required ~
<br />parking area 70,793 sf
<br />mass excavation 12,821 cy 5.00 64,105 64,105
<br />bank cut 1,823 cy 5.00 9,115 9,115
<br />fill under slab 628 cy 7.00 4,396 4,396' w/ on site material
<br />backfill against foundation 3,039 cy 7.00 21,273 21,273 w/ on site material
<br />bus mall area @ sog 42,745 sf
<br />cut 106 cy 5.00 530 ' S30
<br />fill 1,983 cy 7.00 13,881 13,881' w/ on site material
<br />haul 8~ dispose excess material off site 9,100 cy 6.00 54,600 54',600 ,
<br />dewatering 1 sum 25,000.00 25,000 2~,000
<br />elevator pit excavation sum 0.00 0 0 NIC w/ building
<br />structural (foundation) excavation
<br />footings 1,260 cy 15.00 18,900 18,900
<br />ramp wall 22 cy 15.00 324 324
<br />structural (foundation) backfill _...
<br />footings 756 cy 18.00 13,608 1'3,608
<br />ramp wall 14 cy 18.00 245 245
<br />haul & dispose excess material off site 512 cy 6.00 3,072 3'',072
<br />level & grade 113,538 sf 0.10 11,354 11,354
<br />4" gravel under slab 1,472 cy 13.00 19,136 19,136'
<br />vapor barrier 3,353 sf 0.15 503 503 @ strg rm & elevtr Ibby only
<br />Parking Detail Estimate - Page 1