Laserfiche WebLink
BAND FILTER SYSTEM CONSTHUCTION DETAIL SHEET <br /> <br />September 2, 1993 <br /> <br />APPLICANT: JOHN M. KAILEY <br />SITE NUMBER: 93-2718 <br /> <br /> Your site has been found suitable for a SAND FILTER ALTERNATIVE SEWAGE <br />DISPOSAL SYSTEM. The following construction specifications shall apply to the <br />installation of your septic system. <br /> <br /> 1. The septic tank shall have a minimum liquid capacity of 1000 <br /> gallons. <br /> <br /> 2. The projected daily sewage flow for this project is calculated at <br /> 450 qallons per day. Based on soil conditions observed on this <br /> site, the disposal field will be sized at 45 lineal feet per 150 <br /> qallons of projected daily sewage flow. A minimum of 135 lineal <br /> feet of disposal field will be required for your proposed develop- <br /> ment. The disposal trenches are constructed two (2) feet wide and <br /> on minimum ten (10} foot centers and with no line exceeding 125 <br /> feet in length. The trenches and perforated pipe are installed <br /> level (~1") and contoured to follow the natural ground surface. <br /> <br />The disposal field shall be constructed with egual distribution <br />with a minimum trench depth of 12 inches and a maximum trench <br />depth of 12 inches. There must be at least 16 inches of backfill <br />over the top of the gravel, measured from the natural ground <br /> <br />The sand filter system shall be designed and operated as per OAR <br />340-71-290 through 340-71-305. Detailed plans for the system must <br />be submitted prlor to permit issuance. A building permit is <br />required if a site built concrete box is used as the sand filter <br />container. A pamphlet is available in our office which details the <br />requirements for a sand filter system. <br /> <br /> An effluent lift pump may be necessary to construct the disposal field <br />in the approved area and at the correct depth. <br /> <br /> A capping fill is required with this system. The system shall be <br />constructed as indicated on the attached Capping Fill construction detail <br />sheet. <br /> <br /> This approval is site specific to the area tested and the septic system <br />must be located in the immediate area of the test pits unless otherwise autho- <br />rized by this office. A new site evaluation may be required if the system is <br />proposed for a different area on the property. <br /> <br />SPECIAL CONDITIONS~ <br /> The drainfields must be constructed within the immediate area of the <br /> southerly test pit on the highest surface possible. Avoid the northerly <br /> pit which is dug within a concave landform. A pre-construction field <br /> stakeout is ~ecommended to establish the locations and elevations of the <br /> individual drainfield lines of both drainfields. Well construction and <br /> all excavation should be deferred pending the pre-construction stakeout. <br /> Refer to the stakeout procedure and the setback list for details to <br /> complete the stakeout. Note, especially the requirement for the dry soil <br /> summer season limitation for the capping fill part of the installation. <br /> <br />THIS IS NOT A PERMIT TO INSTALL THE SEPTIC SYSTEM. DO NOT INSTALL THE SYSTEM <br />UNTIL A VALID PERMIT HAS HEEN ISSUED HY THIS OFFICE. <br /> <br /> <br />