~,,,; Courthouse Square s~1~9~ <br />Time Schedule ' <br />Key Performance Dates <br />Apri121 Abatement begins <br />May 12 Demolition begins <br />May 19 Complete Architect & Contractor's contract <br />May 10 Publish RFP for project management services <br />May 15 Soft commitments to retail partnership and fmancing <br />May 26 Select project manager <br />June 1 <br />~ Development agreements <br /> Condominium agreement <br /> Ground leases and parking agreements <br /> Employment agreements <br />July 1 Private owner financing commitments <br /> Begin preparation of bond documents <br /> Bid packages <br />July 15 D.D. drawings (shell) <br /> Construction documents (parking, utilities & structurjal) <br /> T.I. budget <br />August 1 Possible date for excavation or further testing <br />August 15 G M P due <br /> Fina1 budget (public and private commitments) , <br />September 1 Construction starts ' <br />~,, Bond sale <br />